5. The EPSON RC+ 5.0 GUI
EPSON RC+ 5.0 (Ver.5.4) User's Guide Rev.4 61
Importing a Controller project
For projects using Vision Guide, the calibration data and model files are not imported from
the Controller because they are not stored there. After import, you will need to re-teach the
vision models and perform the calibrations.
Follow these steps to import a project from a controller:
1. Select Import from the Project Menu to open the Import Project dialog.
2. Select
Controller and click Next. Communications with the controller will be
established if EPSON RC+ 5.0 is not already connected.
3. The destination project name is set to the name of the current project in the controller.
You can modify the destination project name if desired. Select the destination drive
and folder, then click
Next.
)
NOTE